View Procedure
Procedure Name | Granting permission to import goods on the List of goods banned from import for scientific research |
Description |
Category
|
Procedure for licensing
|
Responsible Agency
|
Ministry of Industry and Trade
|
Legal basis of the Procedure
|
Decree 187/2013/ND-CP dated November 20, 2013 of the Government, detailing the Commercial Law regarding international goods purchase and sale and goods purchase and sale agency, processing and transit activities with foreign partners;
Circular 04/2014/TT-BCT Elaborating the implementation of the Government's decree 187/2013/ND-CP which elaborates the regulations on international trade of law on commerce
|
Processing time
|
Within 07 working days from the date of reception of the adequate and valid dossier
|
Fee
|
|
Required documents
No
|
Type of documents
|
Note
|
1
|
Decision on establishment, certificate of investment, certificate of business registration or certificate of enterprise registration
|
A copy with confirmation and affixed seal for copying from original by the applicant
|
2
|
Application for import, clearly declaring the name of goods, HS code, quantity, value of each item enclosed with the certification and commitment of the accuracy of such information
|
1 original copy
|
3
|
Report on the conformity of the prior permit (except for cases of fist time import)
|
1 original copy
|
Process Steps
Step 1
|
The trader (applicant) shall submit via postal service 1 (one) set of dossier of application to the Ministry of Industry and Trade (address: 54 Hai Ba Trung, Hoan Kiem, Ha Noi).
|
Step 2
|
The Ministry of Industry and Trade shall check the validity and completion of the dossier. If the dossier is complete or valid, within 7 (ten) working days, the Ministry of Industry and Trade shall grant the permit on import.
|
Step 3
|
If the dossier is not complete or valid, or in case of refusing to grant the permit, the Ministry of Industry and Trade shall notify in writing or via postal service of contents to be fixed or added to complete the dossier or state relevant reasons for refusal.
|
Step 4
|
The written certification for granting the permit shall be sent to the trader via postal system.
|
Workflow process:

|
Category | Procedure |
Please customize this view
This procedure apply to theses Measures.